Shuttle rotary dimmer
Shuttle DC dimmer
Shuttle 1-10V Dimmer
DFFE Compliance
Mandatory and additional voluntary compliance testing
All Shuttle phase cut dimmers are tested against and comply with the following mandatory requirements (125W, 250W, 500W & 800W bell-press and rotary models)
EMC (SA and EU mandatory)
- CISPR 15 (2018-05 ED.9.00): ‘Limits and methods of measurement of radio disturbance characteristics of electrical lighting and similar equipment’
- SANS 2332 (2017 ED.1.00) / CISPR 32 (2015 ED.2.00): ‘Electromagnetic compatibility of multimedia equipment – Emission requirement’
- IEC 61547 (2009): Equipment for general lighting purposes – EMC immunity requirement
- SANS 61000-3-2 (2009) / IEC 61000-3-2 (2009): Limits for Harmonic Current Emissions (Equipment Input Current ≤16 A per phase)
- SANS 61000-3-3 (2009) / IEC 61000-3-3 (2008) : Limits – Limitation of voltage changes, voltage fluctuations and flicker in public low-voltage supply systems – Equipment with rated current ≤16 A per phase
- SANS 61000-4-2 (2009) / IEC 61000-4-2 (2008): Testing and measurement techniques – Electrostatic discharge immunity test
- SANS 61000-4-3 (2008) / IEC 61000-4-3 (2010): Testing and measurement techniques – Radiated, radio-frequency, electromagnetic field immunity test
- SANS 61000-4-4 (2011) / IEC 61000-4-4 (2011): Testing and measurement techniques – Electrical Fast Transient / Burst
- SANS 61000-4-5 (2006) / IEC 61000-4-5 (2005): Testing and measurement techniques – Surge immunity test
- SANS 61000-4-6 (2009) / IEC 61000-4-6 (2008): Testing and measurement techniques – Immunity to conducted disturbances, induced by radio-frequency fields
- SANS 61000-4-11 (2005) / IEC 61000-4-11(2004): Testing and measurement techniques – Voltage Dips, Short Interruptions and voltage variations immunity test.
Safety and Performance (SA and EU mandatory)
- IEC 60669-1: 2017 / SANS 60669-1: 2017
- IEC 60669-2-1: 2015 / SANS 60669-2-1: 2015
CE/EU Conformance (EU mandatory)
- Directive 2014 / 35 / EU – Low voltage directive (LDV)
- Directive 2014 / 30 / EU – EMC directive (EMCD) in conjunction with directive 89/336/EEC as amended with 91/31/EEC
AS/NSZ Conformance (AS/NSZ mandatory) – all Shuttle bell-press dimmer models
- AS/NSZ 60669-1: 2013
- AS/NSZ 60669-2-1: 2013
- SGS-190520-EA
- SGS-190521-EA
Shuttle SDIM-T-LED-500W complies with the following voluntary requirements
IEC EMC (voluntary)
- SANS 61000-4-4 (2011) / IEC 61000-4-4 (2011): Testing and measurement techniques – Electrical Fast Transient / Burst immunity.
- Live to Neutral: Tests were executed with
- Mandatory test level
- +1kV and -1kV interference signal amplitudes for a 60 second period for each polarity.
- Over tests levels
- +2kV and -2kV interference signal for a 60 second period for each polarity
- +3kV and -3kV interference signal for a 60 second period for each polarity
- +4kV and -4kV interference signal for a 60 second period for each polarity
- +4.4kV and -4.4kV interference signal for a 60 second period for each polarity
- +4.8kV and -4.8kV interference signal for a 60 second period for each polarity
- Mandatory test level
- SANS 61000-4-5 (2006) / IEC 61000-4-5 (2005): Testing and measurement techniques – Surge immunity test
- Mandatory test level
- Live to Neutral ± 1kV
- Over tests levels
- Live to Neutral ± 2kV
- Live to Neutral ± 3kV
- Live to Neutral ± 3.5kV
- Mandatory test level
Supply Voltage Increase (Not a standard test method)
- Continuous over-voltage of a maximum level of 280VAC on the power input for 5 minutes
Load Short Circuit (Not a standard test method) – applies to all dimmer models
- Continuous short circuited load. Dimmer resumes normal operation after removal of the short circuit
Shuttle 96W DC bell-press dimmer is tested against and comply with the following mandatory requirements
EMC (mandatory)
- CISPR 15 (2018-05 ED.9.00): ‘Limits and methods of measurement of radio disturbance characteristics of electrical lighting and similar equipment’
- SANS 2332 (2017 ED.1.00) / CISPR 32 (2015 ED.2.00): ‘Electromagnetic compatibility of multimedia equipment – Emission requirement’
- IEC 61547 (2009): Equipment for general lighting purposes – EMC immunity requirement
- SANS 61000-4-2 (2009) / IEC 61000-4-2 (2008): Testing and measurement techniques – Electrostatic discharge immunity test
- SANS 61000-4-3 (2008) / IEC 61000-4-3 (2010): Testing and measurement techniques – Radiated, radio-frequency, electromagnetic field immunity test
- SANS 61000-4-4 (2011) / IEC 61000-4-4 (2011): Testing and measurement techniques – Electrical Fast Transient / Burst
Safety and Performance (EU mandatory)
- IEC 61347-2-13: 2014 / AMD1: 2016 used in conjunction with IEC 61347-1: 2015
CE/EU Conformance (EU mandatory)
- Directive 2014 / 35 / EU – Low voltage directive (LDV)
- Directive 2014 / 30 / EU – EMC directive (EMCD) in conjunction with directive 89/336/EEC